Construction Progress Update – 05/13/2024
The project continues to move forward despite the recent weather issues. Site work on the West Field has restarted as we remove excess soils, establish final grades, and begin placement of the pathways that will support the school’s Physical Education and recess activities. The Interior Finishes work continues – working first from floor three, then floor two, and completing the interior finishes work on floor one. The new addition and the gym have now been completely closed-in as interior painting work begins – first on the ceiling, then the walls. Ceramic tiling of all toilet rooms advances ahead of schedule and toilet fixture installation follows directly behind this Work Result.