Construction Progress Update – 08/19/2024
In the 1929 and1995 buildings, the final cleaning stage is in progress. New classroom furniture has been delivered and installed. The existing teacher materials have been loaded into the classrooms to be available for the scheduled arrival of the teachers on August 21st. The gym, band room, and art room will not open with the school on September 3rd but will be available at the end of October. Site improvements at the West Field will be completed by the first day of school, providing new play areas for the children – including grass play areas and a ball court. The East Fields will be completed in the fall of 2024 as the project closes out by year end.