Construction Progress Update – 10/31/2022

Temporary School Campus final professional acceptance affidavits have been issued and sent to the building inspector as a prerequisite for issuance of the CO. Currently, the final plumbing connections, electrical and fire alarm systems are nearing completion. We learned this week that the electric utility will have power to the site no later than 11/18 following a major primary infrastructure upgrade. The plan is to move into the Temp School during Thanksgiving Week with Day-One being 11/28. CHA is leading the move management strategic plan with the assistance of a local moving company and school staff.