OPM Qualifications Process

  • Three responses to Request for Qualifications (RFQ) for an Owner’s Project Manager (OPM) opened and interviews scheduled for early September. Interview questions developed with community input.
  • Begin discussion of Request for Qualifications for architect/designer.
  • Discussions of  alternative funding opportunities beyond taxes to support the building project.
  • Continued communication from the School Committee concerning the deteriorated conditions at the school, with the emphasis that these issues are being addressed by the Selectmen and School Committee, not the TSBC.