Construction Progress Update – 7/21/2023
The Tisbury School Addition and Renovation Project continues to progress as construction moves forward on the new gym and administration additions. The new administration wing foundations have been poured and damp-proofing is currently being installed. Primary electric underground conduit runs are being installed. Street openings are in progress on Spring Street to bring in the required underground utilities. Structural steel is being erected at the new gym additions. Eight truckloads of steel have been delivered to-date and 1 to 2 trucks will arrive daily until the end of July. Metal decking and joist installation will be completed by the end of this month. Light-gauge metal partition wall framing work is ongoing in the 1929 and 1995 buildings. Acoustic spray ceiling insulation on the third floor has been installed and painted white. Interior plumbing and electrical rough in has begun within the 1929 building. Exterior masonry restoration and window lintel replacement continues. The site contractor is installing drainage structures and associated piping.